Sunday, October 26, 2014

Work Completed

The work included in the 2014 MFT Street Resurfacing project within the Estate Lane Neighborhood and other Village streets is substantially completed at this time. There are only a few minor repairs that still need to be performed associated with landscape restoration, concrete curb & gutter repair, and other miscellaneous items. We anticipate these repairs to be made within the next few weeks prior to the end of the construction season.

This will be the final blog post of the 2014 MFT project, including the Estate Lane Improvements.

If you have any additional questions or concerns please contact the project manager, Adriana Webb at 847-904-4414.

Thank you again for your patience throughout the construction season as work along your streets and within your neighborhoods was completed.

Monday, October 20, 2014

Estate Lane Improvements Nearly Complete. Minor Items Remaining

Estate Lane Improvements:

Last Week:
·         Asphalt paving of surface layer
·         Damaged concrete curb & gutter removed.
·         Grading and installation of topsoil.
·         Asphalt patching performed in areas that shows signs of failure
·         Completed most of the sod restoration.

This Week:
·         Complete Sod Restoration
·         Concrete curb & gutter that was damaged and previously removed to be installed.

Thank you again for your patience and understanding as the work is coming to an end. Hopefully you are satisfied and happy with the improvements that were made within the neighborhood.

Friday, October 10, 2014

Landscaping to Begin Next Week. Asphalt Binder Installed.

Estate Lane Improvements:

Last Week:
·         Arrow Road completed grading and shaping of the existing roadway.
·         Arrow Road paved the asphalt binder layer
·         Landscape restorations scheduled to begin on Saturday, October 11th 

Next Week:
·         Following completion of landscape restoration, the final asphalt surface layer will be installed. 
 
Thank you for your patience as you dealt with the construction over the past few weeks and inconveniences that come with this work. As the landscaping is completed, the end of the project is near.

Saturday, October 4, 2014

Asphalt Paving Next Week

Estate Lane Improvements:
Last Week:
·         Suburban Concrete completed the installation of concrete sidewalks and curb & gutter.
·         Arrow Road installed the asphalt driveways.
·         Arrow Road completed the pavement removal / milling along the project site 

Next Week:
·         Arrow Road to perform roadway grading and preparation work prior to asphalt paving.
·         Arrow Road will complete the asphalt binder layer along the entire roadway, scheduled for Tuesday.
·         Landscape restoration, depending on weather conditions.

With the asphalt paving scheduled for next week, the major construction is nearing completion. We ask that you do not park along the roadway during the grading and paving operations.

Thank you for your patience and understanding during the entire construction process, especially those residents who were unable to access their driveways for an extended period of time during the concrete work.