Friday, July 25, 2014

Asphalt Paving Along Covert Road and Huber Lane Completed

Work Completed last week:
·         Existing asphalt pavement removal and patching along:
o   Covert Road from Washington Road to Michael Manor
o   Huber Lane from Central Road to northerly cul-de-sac
·         Asphalt paving of asphalt binder and surface along:
o   Covert Road from Washington Road to Michael Manor
o   Huber Lane from Central Road to northerly cul-de-sac 

Anticipated work next week includes:
Arrow Road (Roadway Improvements):
·         Partial pavement removal and replacement at various locations within The Glen residential neighborhoods along:
o   West Lake Avenue
o   Shermer Road
o   Saratoga Lane
o   Monterey Drive
o   Independence Avenue
o   Constitution Drive
o   Primrose Lane
o   Indigo Lane 

Residents will be notified of work performed within the area and any parking restrictions. 

Landscape Contractor:
·         Topsoil & seed restoration of lawns along:
o   Covert Road from Washington to Michael Manor
o   Huber Lane from Central road to northerly cul-de-sac. 

We apologize for the inconvenience of the construction work within your neighborhoods and along your streets.  

Friday, July 18, 2014

Pavement Removal and Asphalt Paving along Covert & Huber Next Week

Work Completed last week:
Suburban Concrete (Concrete Improvements):
·         Concrete curb & gutter, sidewalk, and driveway replacements along:
o   South side of Covert Road from Washington Road to Michael Manor
o   East side of Huber Lane from Central to northerly cul-de-sac, including cul-de-sac

Anticipated work next week includes:
Arrow Road (Roadway Improvements):
·         Existing asphalt pavement removal and patching along:
o   Covert Road from Washington Road to Michael Manor
o   Huber Lane from Central Road to northerly cul-de-sac
·         Asphalt Paving along:
o   Covert Road from Washington Road to Michael Manor
o   Huber Lane from Central Road to northerly cul-de-sac
                                                                 
During the asphalt pavement removal, patching, and asphalt paving process we ask that you do not park on the street. Residents will have access to their driveways. Residents will be notified detailing the work to be performed and restrictions during the construction operations.

We apologize for the inconvenience of the construction work within your neighborhoods and along your streets.  

Saturday, July 12, 2014

Concrete Work on Covert and Huber Continues

Work Completed last week:
Suburban Concrete (Concrete Improvements):
·         Concrete curb & gutter, sidewalk, and driveway replacements along:
o   North side of Covert Road from Washington Road to Michael Manor
o   West side of Huber Lane from Central to northerly cul-de-sac

 Landscape Contractor:
·         Glen Lake Estates Neighborhood
o   Installed topsoil and seed behind the concrete curb & gutter and sidewalks that were previously replaced.
·         Glenview Public Library Parking Lot south of Glenview Road
o   Installed topsoil and seed behind the concrete curb & gutter that was previously replaced.

Anticipated work next week includes:
Suburban Concrete (Concrete Improvements):
·         Concrete curb & gutter, sidewalk, and driveway replacements along:
o   South side of Covert Road from Washington Road to Michael Manor
o   East side Huber Lane from Central Road to northerly cul-de-sac, including cul-de-sac
·         Residents have been notified regarding timing of the construction and access restrictions to their driveways.

Landscape Contractor:
·         Glenview Public Library Parking Lot south of Glenview Road
o   Complete installation of topsoil and seed behind the concrete curb & gutter that was previously replaced. 

We apologize for the inconvenience of the construction work within your neighborhoods and along your streets. Thank you for your patience and understanding while you are unable to utilize your driveways.

Thursday, July 3, 2014

Glen Lake Estates Neighborhood Paved

Work Completed last week:
Arrow Road (Roadway Improvements):
·         Glenlake Estates Neighborhood
o   Paved asphalt surface along entire neighborhood.
o   Completed asphalt patching of driveways where concrete curb & gutter or sidewalk repairs were made. 

Anticipated work next week includes:
Suburban Concrete (Concrete Improvements):
·         Concrete curb & gutter and sidewalk replacements along:
o   Covert Road from Washington Road to Michael Manor
o   Huber Lane from Central Road to northerly cul-de-sac.
·         Residents have been notified regarding timing of the construction and access restrictions to their driveways.

Arrow Road (Roadway Improvements):
·         No work anticipated.

Landscape Contractor:
·         Glen Lake Estates Neighborhood
o   Install topsoil and seed behind the concrete curb & gutter and sidewalks that were previously replaced and clean up any remaining construction debris.
·         Glenview Public Library Parking Lot south of Glenview Road
o   Install topsoil and seed behind the concrete curb & gutter that was previously replaced. 

We apologize for the inconvenience of the construction work within your neighborhoods and along your streets.