Monday, October 20, 2014

Estate Lane Improvements Nearly Complete. Minor Items Remaining

Estate Lane Improvements:

Last Week:
·         Asphalt paving of surface layer
·         Damaged concrete curb & gutter removed.
·         Grading and installation of topsoil.
·         Asphalt patching performed in areas that shows signs of failure
·         Completed most of the sod restoration.

This Week:
·         Complete Sod Restoration
·         Concrete curb & gutter that was damaged and previously removed to be installed.

Thank you again for your patience and understanding as the work is coming to an end. Hopefully you are satisfied and happy with the improvements that were made within the neighborhood.