Asphalt Paving Next Week

Estate Lane Improvements:
Last Week:
·         Suburban Concrete completed the installation of concrete sidewalks and curb & gutter.
·         Arrow Road installed the asphalt driveways.
·         Arrow Road completed the pavement removal / milling along the project site 

Next Week:
·         Arrow Road to perform roadway grading and preparation work prior to asphalt paving.
·         Arrow Road will complete the asphalt binder layer along the entire roadway, scheduled for Tuesday.
·         Landscape restoration, depending on weather conditions.

With the asphalt paving scheduled for next week, the major construction is nearing completion. We ask that you do not park along the roadway during the grading and paving operations.

Thank you for your patience and understanding during the entire construction process, especially those residents who were unable to access their driveways for an extended period of time during the concrete work.