Friday, August 8, 2014

Partial Pavement Removal and Replacement along Various Roadways to Continue Next Week.

Work Completed last week:
Arrow Road (Roadway Improvements):
·         Partial pavement removal and replacement at various locations within The Glen residential neighborhoods along:
o   Tanglewood Drive
o   Saratoga Lane
o   Monterey Drive
o   Independence Avenue
o   Constitution Drive
o   Primrose Lane
o   Indigo Lane

Anticipated work next week includes:
Arrow Road (Roadway Improvements):
·         Partial pavement removal and replacement at various locations within the Village along arterial roadways including:
o   West Lake Avenue
o   Lehigh Avenue
o   Chestnut Avenue
o   Central Road

Landscape Contractor
o   Installing topsoil and performing cleanup work on the previously paved sections of Covert Road and Huber Lane. 

Thanks again for your patience and understanding as we rehabilitate several roadways within the Village. We apologize for the delays and inconvenience this work causes to daily traffic.

Once the partial pavement removal and replacement along the arterial roadways is completed, a majority of the work associated with the 2014 MFT project will be completed. The remaining items to be completed include the asphalt resurfacing on Chatham Road, various landscape restorations, and other miscellaneous items. The 2” asphalt removal and replacement on Chatham Road is scheduled to begin later this month with Nicor Gas finishing their work on Chatham by the end of next week.    

However, the work along Estate Lane is just beginning. It is anticipated that underground utility cleaning and repairs will begin in the next 1 to 2 weeks. The blog posts will continue to inform those residents of the construction progress along Estate Lane, but that will be the only consistent work.