Work Completed last week:
Arrow Road, Paving Contractor
·         Partial pavement removal and replacement (MARS) at various locations within the Village including:
o   West Lake Avenue
o   Lehigh Avenue
o   Chestnut Avenue
o   Glenview Road
o   Fir Street
o   Evergreen Terrace
·         Chatham Road from Glenview Road to south end:
o   Existing pavement removal
o   Asphalt patching
o   Paved new asphalt surface 

Landscape Contractor
o   Installed topsoil and seed along Covert Road and Huber Lane.

Work Remaining to be completed:
·         Partial pavement removal and replacement along Central Road
·         Landscape restoration at southeast end of Chatham 

Estate Lane Improvements:
Last Week:
·         American Underground, the sewer televising contractor, cleaned and televised remaining section of existing storm sewer.
·         Humir Construction, the underground contractor, started storm sewer repairs.

Next Week:

·         Humir Construction to continue working on storm sewer repairs. It is anticipated that all underground work will be completed by the end of the week.

Concrete sidewalk and curb & gutter repairs are not anticipated to begin until after the Labor Day weekend.