Friday, July 18, 2014

Pavement Removal and Asphalt Paving along Covert & Huber Next Week

Work Completed last week:
Suburban Concrete (Concrete Improvements):
·         Concrete curb & gutter, sidewalk, and driveway replacements along:
o   South side of Covert Road from Washington Road to Michael Manor
o   East side of Huber Lane from Central to northerly cul-de-sac, including cul-de-sac

Anticipated work next week includes:
Arrow Road (Roadway Improvements):
·         Existing asphalt pavement removal and patching along:
o   Covert Road from Washington Road to Michael Manor
o   Huber Lane from Central Road to northerly cul-de-sac
·         Asphalt Paving along:
o   Covert Road from Washington Road to Michael Manor
o   Huber Lane from Central Road to northerly cul-de-sac
                                                                 
During the asphalt pavement removal, patching, and asphalt paving process we ask that you do not park on the street. Residents will have access to their driveways. Residents will be notified detailing the work to be performed and restrictions during the construction operations.

We apologize for the inconvenience of the construction work within your neighborhoods and along your streets.