Friday, July 25, 2014

Asphalt Paving Along Covert Road and Huber Lane Completed

Work Completed last week:
·         Existing asphalt pavement removal and patching along:
o   Covert Road from Washington Road to Michael Manor
o   Huber Lane from Central Road to northerly cul-de-sac
·         Asphalt paving of asphalt binder and surface along:
o   Covert Road from Washington Road to Michael Manor
o   Huber Lane from Central Road to northerly cul-de-sac 

Anticipated work next week includes:
Arrow Road (Roadway Improvements):
·         Partial pavement removal and replacement at various locations within The Glen residential neighborhoods along:
o   West Lake Avenue
o   Shermer Road
o   Saratoga Lane
o   Monterey Drive
o   Independence Avenue
o   Constitution Drive
o   Primrose Lane
o   Indigo Lane 

Residents will be notified of work performed within the area and any parking restrictions. 

Landscape Contractor:
·         Topsoil & seed restoration of lawns along:
o   Covert Road from Washington to Michael Manor
o   Huber Lane from Central road to northerly cul-de-sac. 

We apologize for the inconvenience of the construction work within your neighborhoods and along your streets.