Due to weather conditions and threats of rain throughout the past week, a limited amount of work was completed versus what was originally scheduled.

Work Completed last week:
Suburban Concrete (Concrete Improvements):
·         Completed concrete curb & gutter and sidewalk replacements at the Glenview Public Library parking lot south of Glenview Road.
·         Completed concrete curb & gutter and sidewalk replacements within the Glen Lake Estates neighborhood.

Arrow Road (Roadway Improvements):
·         Milled existing asphalt pavement and performed asphalt patching at the Glenview Public Library parking lot south of Glenview Road. 

Humir Construction (Underground Utility Improvements):
·         Performed underground utility repairs and installations along:
o    Covert Road from Washington Road to Michael Manor

Landscapers also installed topsoil and sod along Grove Street between Roosevelt and Spruce.

 Anticipated work next week includes:
Suburban Concrete (Concrete Improvements):
·         Begin concrete curb & gutter and sidewalk replacements along:
o   Covert Road from Washington Road to Michael Manor
o   Huber Lane from Central Road to northerly cul-de-sac.
·         Residents will be notified prior to concrete work on their street. Details will be given regarding timing of the construction and access restrictions to your driveways.

 Arrow Road (Roadway Improvements):
·         Public Library parking lot south of Glenview Road:
o   Installing new asphalt surface layer
o   Pavement marking
·         Glenlake Estates Neighborhood 
o   Milling of the existing asphalt surface.
o   Asphalt patching of driveways where concrete curb & gutter or sidewalk repairs were made.
·         Partial Pavement Removal and Asphalt Paving as part of the MARS program along:
o   Strawberry Lane:  Maple Leaf and Winnetka Road
o   Indian Ridge Court: Indian Ridge Drive to South cul-de-sac
o   Maple Leaf:  Pfingsten Road to Strawberry Lane

Humir Construction (Underground Utility Improvements)
·         No work anticipated.